Tips on Time and Work

1. If a person can do a piece of work in ‘X’ days, then person one day work is (1 / X)

2. If a person 1 day’s work is (1 / X) then the person will complete the work in ‘X’ days.

3. While solving the problems assume the work done by person to be equal to 1.

 

Time and work online test Online Test - 1 (Time and Work) TAKE TEST

Number of questions : 20  |  Time : 30 minutes

Time and work online test Online Test - 2 (Time and Work) TAKE TEST

Number of questions : 20  |  Time : 30 minutes

Time and work online test Online Test - 3 (Time and Work) TAKE TEST

Number of questions : 20  |  Time : 30 minutes

Time and work online test Online Test - 4 (Time and Work) TAKE TEST

Number of questions : 20  |  Time : 30 minutes




Previous year  Time and Work Question and Answer

Question-1)

A alone can do a piece of work in 6 days, B alone can do the same work in 12 days. In how many days can A and B together completes the same work?

A) 5 days
B) 4 days
C) 3 days
D) 2 days
E) None of these

Ans: B

Solution:

A’s 1 day’s work = (1 / 6)
B’s 1 day’s work = (1 / 12)
(A + B)’s 1 day’s work = $(1 / 6) + (1 / 12) = (1 / 4)$
Therefore (A + B) will complete the work in 4 days.


Question-2)

3 men can do a piece of work in 18 days. 6 children can also do that work in 18 days. 4 men and 4 children together will finish the work in how many days?

A) 10
B) 6
C) 12
D) 9
E) None of these

Ans: D

Solution:

Using the below formulae $M1×D1×W2 = M2×D2×W1$
⇒ $3 × 18 × 1 = 6 × D2 ×1$
⇒ D2 = 9 days

Question-3)

Ravi gets Rs. 110 for every day that he works. If he earns Rs. 2750 in a month of 31 days, for how many days did he work?

A) 25 days
B) 28 days
C) 26 days
D) 24 days
E) None of these

Ans: A

Solution:

Required number of days = $2750 / 110$ = 25 days

 

Question-4)

A can do $1/3$ of a work in 5 days and B can do $2/5$ of the work in 10 days. In how long both A and B together can take the necessary steps?

A) $31/4$ days

B) $24/5$ days

C) $75/8$ days

D) 15 days

Solution:
Answer:C

$1/3$ work is done by A in 5 days.
Whole work will be done by A in 15 days.
$2/5$ work is done by B in 10 days.
Whole work will be done by B in $(10×5/2)$ day’s     i.e 25 days
(A+B) ’s 1 days work = $(1/15+1/25)$ = $8/75$
∴A and B can do the work in $75/8$ days

 

Question-5)

A and B can do a bit of work in 45 days and 40 days. they started the work together however A leaves after a few days and B completed the remaining work in 23 days. After how long did A leaves?

A) $2/3$ days

B) 5 days

C) 9 days

D) 15 days

Answer : C
Solution:

Work done by B in 23 days = $(23 × 1/40) = 23/40$ ; remaining work = $(1- 23/40)= 17/40$
(A+B)’s 1 day work = $( 1/45 + 1/40)$ = ${8+9}/360$ = $17/360$
$17/360$ work is done by (A+B) in 1 day.
$17/40$ work is done by them in $(360/17 × 17/40)$ = 9 days