Nowadays competitive exams became very tough for candidates who are preparing competitive exams like SSC CGL, SSC CHSL, SSC MTS, Group D, Police Jobs, Banking, etc, though all most of the candidates have aptitude solving skills but they don't know how to solve it in less time or you can say they don't know time management, here you will how to solve the time and work aptitude questions with less time by using some simple tricks.
If $M_1$ men can finish $W_1$ work in $D_1$ days and $M_2$ men can finish $W_2$ work in $D_2$ days then, Relation is
If M1 men finish W1 work in D1 days, working T1 time each day and M2 men finish W2 work in D2 days, working T2 time each day, then
If A completes a piece of work in 'x' days, and B completes the same work in 'y' days, then,
Question-1)
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs.3200. With the help of C they completed the work in 3 days. How much is to be paid to C ?
a) Rs.375
b) Rs.400
c) Rs.800
d) Rs.600
Solutions:
A’s 1 day’s work = $1/6$
B’s 1 day’s work = $1/8$
(A + B + C)’s 1 day’s work = $1/3$
C’s 1day’s work
= $1/3 - 1/6 - 1/8 = {8 - 4 - 3}/24 = 1/24$
Ratio of their one day’s work respectively
= $1/6 : 1/8 : 1/24$ = 4 : 3 : 1
Sum of the ratios = 4 + 3 + 1 = 8
C’s share = Rs.$1/8$ × 3200 = Rs.400